Evaluasi Keandalan Buffer CCPM Melalui Back-Testing Fever Chart dan Rantai Markov pada Proyek Kompresor Bertekanan Sangat Rendah

Authors

  • Danur Widyanto Institut Teknologi Kalimantan, Balikpapan, Indonesia
  • Lusi Ernawati Institut Teknologi Kalimantan, Balikpapan, Indonesia
  • Samsu Dlukha Nurcholik Institut Teknologi Kalimantan, Balikpapan, Indonesia
  • Rizqy Romadhona Ginting Institut Teknologi Kalimantan, Balikpapan, Indonesia
  • Thorikul Huda Institut Teknologi Kalimantan, Balikpapan, Indonesia
  • Muqimuddin Muqimuddin Institut Teknologi Kalimantan, Balikpapan, Indonesia

DOI:

https://doi.org/10.38035/jimt.v8i1.9921

Keywords:

Critical Chain Project Management, Buffer Consumption Index, Fever Chart, Rantai Markov, keandalan penjadwalan

Abstract

Perilaku dinamis buffer selama pelaksanaan proyek masih kurang dipahami apabila penilaian kinerja hanya mengandalkan satu indikator pada akhir proyek. Penelitian ini bersifat studi kasus tunggal yang retrospektif/kontrafaktual: penelitian ini mengajukan kerangka back-testing dinamis yang mengintegrasikan Schedule-Weighted Progress Analysis (SWPA), Buffer Consumption Index (BCI), pemantauan Fever Chart, serta model rantai Markov yang bersifat eksploratif. Kerangka ini diterapkan pada tiga skenario Root Square Error Method (RSEM) dengan pengurangan durasi aktivitas sebesar p = 30%, 40%, dan 50%. Evaluasi SWPA terhadap 815 aktivitas menunjukkan progres aktual tertinggal jauh dari rencana pada tahap awal proyek, dengan Indeks Progres Jadwal mencapai 0,064 pada Minggu ke-16. Back-testing BCI mengungkap sebuah paradoks: skenario p = 50% menghasilkan durasi komitmen CCPM terpendek (318 hari), namun BCI akhir terendah (3,24), yang menunjukkan ketahanan buffer proporsional terkuat berdasarkan metrik ini. Sementara itu, skenario p = 30%, yang paling presisi dalam mencocokkan estimasi analitis dengan simulasi jaringan (selisih 0,7%), justru menghasilkan BCI akhir yang paling tinggi (3,69). Fever Chart menunjukkan proyek memasuki Zona Merah pada minggu ke-20 dari 61 minggu pengamatan dan tidak pernah pulih; model rantai Markov dengan pemulusan Laplace mengindikasikan persistensi tinggi dalam kondisi Zona Merah. Mekanisme catch-up dalam Critical Chain menyerap 47,5 – 85,4% keterlambatan individual sebelum merambat hingga tingkat proyek. Temuan menunjukkan bahwa penentuan ukuran buffer yang optimal secara matematis tidak menjamin keandalan operasional, sehingga menegaskan perlunya pemantauan Fever Chart secara berkala selama pelaksanaan.

References

Cooper Ordoñez, R. E., Vanhoucke, M., Coelho, J., Anholon, R., & Novaski, O. (2019). A study of the critical chain project management method applied to a multiproject system. Project Management Journal, 50(3), 322–334. https://doi.org/10.1177/8756972819832203

Davalu, B., Khosravi, M. J., Sheikhi, M. S., & Sheikhi, H. (2019). Comparison of the critical path method and critical chain project management effectiveness using inferential statistics in dam construction projects. Journal of Scientific and Engineering Research, 6(8), 53–62.

Ensannudin, & Perdana, S. (2023). Implementation of lean project management in the oil pipeline replacement project in the Rokan area. Nusantara of Engineering, 6(2), 109–117. https://doi.org/10.29407/noe.v6i2.21095

Ghaffari, M., & Emsley, M. W. (2015). Current status and future potential of the research on critical chain project management. Project Management Journal, 46(1), 54–70. https://doi.org/10.1002/pmj.21482

Goldratt, E. M. (1997). Critical chain. North River Press.

Habibie, Y. H., & Ingketria, E. (2025). Update on oil and gas security: Indonesia. In Proceedings of the 8th Oil and Gas Security Network Forum

Ibaad, M. I., Siringoringo, M., Purnamasari, I., Yuniarti, D., & Suyitno. (2025). Application of the fuzzy time series Markov chain method to forecast electronic money transaction values in Indonesia. Jurnal Gaussian, 14(2), 290–301. https://doi.org/10.14710/j.gauss.14.2.290-301

Leach, L. P. (1999). Critical chain project management improves project performance. Project Management Journal, 30(2), 39–51. https://doi.org/10.1177/875697289903000207

Ljiljanić, N., Rajić, Z., & Paunović, T. (2022). Use of PERT (program evaluation and review technique) and PDM (precedence diagramming method) in organizing modern vegetable seedling production. Ekonomika Poljoprivrede, 69(1), 119–138. https://doi.org/10.5937/ekoPolj2201119L

Loban, J. M. (2022). Analisis Markov untuk perpindahan merek kartu GSM (studi kasus mahasiswa FMIPA Universitas Tribuana Kalabahi). Jurnal Ilmiah Wahana Pendidikan, 8(2), 151–158. https://doi.org/10.5281/zenodo.6090242

Maheswari, J. U., Charlesraj, V. P. C., Goyal, A., & Mujumdar, P. (2015). Application of relationship diagramming method (RDM) for resource-constrained scheduling of linear construction projects. Procedia Engineering, 123, 308–315. https://doi.org/10.1016/j.proeng.2015.10.095

Mahmoodzadeh, A., Mohammadi, M., Abdulhamid, S. N., Nejati, H. R., Gharrib Noori, K. M., Ibrahim, H. H., & Hama Ali, H. F. (2021). Predicting construction time and cost of tunnels using Markov chain model considering opinions of experts. Tunnelling and Underground Space Technology, 116, 104109. https://doi.org/10.1016/j.tust.2021.104109

Martens, A., & Vanhoucke, M. (2017). A buffer control method for top-down project control. European Journal of Operational Research, 262(1), 274–286. https://doi.org/10.1016/j.ejor.2017.03.034

Mirayudia, L. E. G., Bintana, I. B. P., & Paramita, I. G. A. P. D. (2021). Analysis of lean construction methods and CCPM scheduling in reducing non-physical construction waste (case study: PKP-PK building construction project at I Gusti Ngurah Rai Airport). Proceedings of the National Vocational Civil Engineering Seminar, 9(1), 274–282.

Newbold, R. C. (1998). Project management in the fast lane: Applying the theory of constraints. CRC Press.

Nisar, A., & Suzuki, K. C. (2015). Critical activity effect on project duration in precedence diagram method scheduling network. In Proceedings of the International Conference on Operations Research and Enterprise Systems (ICORES) (pp. 314–322). https://doi.org/10.5220/0005281503140322

Nugroho, D. T., & Suroso, A. (2023). Penggunaan critical chain project management method terhadap perencanaan waktu pelaksanaan fly over jalan tol. Jurnal Konstruksia, 14(2), 44–65. https://doi.org/10.24853/jk.14.2.44-65

Oliveira, J., & Santos, J. (2015). Critical activity effect on project duration in the precedence diagram method. In Proceedings of the 2nd International Conference on Information Systems Security and Privacy (ICISSP) (pp. 367–374).

Peng, J., & Peng, C. (2022). Buffer sizing in critical chain project management by brittle risk entropy. Buildings, 12(9), 1390. https://doi.org/10.3390/buildings12091390

Piney, C. (2017). A new view of the precedence diagramming model. PM World Journal, 6(1), 1–12.

Project Management Institute. (2019). The standard for earned value management (ANSI/PMI 19-006-2019). Project Management Institute.

Rudeli, N., Santilli, A., Puente, I., & Viles, E. (2017). Statistical model for schedule prediction: Validation in a housing-cooperative construction database. Journal of Construction Engineering and Management, 143(11), 04017083. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001396

Sarwani, S., Baihaqi, I., & Utomo, C. (2024). Causes of delay in EPC projects: The case of Indonesia. International Journal on Advanced Science, Engineering and Information Technology, 14(2), 618–628. https://doi.org/10.18517/ijaseit.14.2.19744

She, B., Chen, B., & Hall, N. G. (2021). Buffer sizing in critical chain project management by network decomposition. Omega, 102, 102382. https://doi.org/10.1016/j.omega.2020.102382

Soltan, S., & Ashrafi, M. (2025). Application of reinforcement learning for integrating project risk analysis and risk response planning: A case study on construction projects. Journal of Project Management, 10, 71–86. https://doi.org/10.5267/j.jpm.2024.11.001

Son, B.-Y., & Lee, E.-B. (2019). Using text mining to estimate schedule delay risk of 13 offshore oil and gas EPC case studies during the bidding process. Energies, 12(10), 1956. https://doi.org/10.3390/en12101956

Sugiyanto, & Umam, A. N. (2021). Analysis of project implementation time performance using the performance intensity method. Rang Teknik Journal, 4(1), 52–67. https://doi.org/10.31869/rtj.v4i1.2100

Sukmono, T., & Lesmana, M. S. (2023). Implementasi Markov chain untuk meminimumkan biaya perawatan mesin spiral menggunakan enumerasi sempurna. Jurnal Teknik Industri, 9(1), 132–143. https://doi.org/10.24014/jti.v8i2.21081

Tian, M., Liu, R. J., & Zhang, G. J. (2019). Solving the resource-constrained multi-project scheduling problem with an improved critical chain method. Journal of the Operational Research Society, 71(8), 1243–1258. https://doi.org/10.1080/01605682.2019.1609883

Widyanto, D., Ernawati, L., Nurcholik, S. D., Ginting, R. R., & Huda, T. (2026). Comparative evaluation of Critical Path Method and Critical Chain Project Management for ultra low-pressure compressor installation in the oil and gas industry. International Journal of Marine Engineering Innovation and Research, 11(2), 566–577. https://doi.org/10.12962/j25481479.v11i2

Wijaya, D. E., Rasyid, N. A., Tandirerung, N. W., Rahayu, M. A., Al Faruqi, F., Ekasari, M., Erliana, D., & Putri, A. R. (2024). Application of the Markov chain method to predict rice crop yields in Bulukumba Regency. Journal of Mathematics, Computations, and Statistics, 7(2), 323–338. https://doi.org/10.35580/jmathcos.v7i2.4432

Wilkens, T. T. (2000). Critical path, or chain, or both? PM Network, 14(7), 68–74.

Downloads

Published

2026-10-16

How to Cite

Widyanto , D., Lusi Ernawati, Nurcholik, S. D., Ginting, R. R., Huda, T., & Muqimuddin, M. (2026). Evaluasi Keandalan Buffer CCPM Melalui Back-Testing Fever Chart dan Rantai Markov pada Proyek Kompresor Bertekanan Sangat Rendah. Jurnal Ilmu Manajemen Terapan, 8(1), 345–364. https://doi.org/10.38035/jimt.v8i1.9921